Casita foundation now about 95% complete. Foundation should be done on Monday. Electrical rough-in at about 75%. Plumbing started. Block work starts on Monday or Tuesday so we should have walls by end of week.
Moving along nicely.
Of course we still have time for the beach at the end of the day!
Some more unwanted wildlife.....Some things just shouldn't be allowed on the beach in public!!!!!